Duggan Drive shared path, Cowaramup

Construction of a new shared path along Duggan Drive, Cowaramup will begin in December 2025.


To minimise disruption to Cowaramup Primary School, works will be done during the summer school holidays. 

The path will be constructed in two stages:
Stage 1. Western portion scheduled to begin 8 December and completed by 23 December 2025.
Stage 2. Eastern portion scheduled to begin works 5 January 2026 for approximately 1 week.

Stage 1 – scheduled to begin on 8 December 2025
Map1.png
Map2.png
Map3.png

Stage 2 - scheduled to start from 5 January 2026
Map4.png

This project is jointly funded by the State Government and the Shire as a part of the WA Bicycle Network Grants Program. 

Duggan Drive was identified as a gap in our path network in the Shire's 2016 Pathway Plan. The new path will provide a link between Symphony Waters and Cowaramup Primary School.

Since that time, the visitation and population has grown and so greater priorities for Cowaramup have been identified through the Cowaramup Integrated Transport Strategy (ITS).

We are working with local volunteers in the Cowaramup Transport Working Group to reassess pathway priorities, which will guide future investment in the area.

The Shire of Augusta Margaret River is also preparing a new pathway plan.

Concept Plans
The Concept Plans have been finalised and are available to view online.
 
07 Oct 2025 Topic Type
Public Notice